Oakes
Irrigation Research Site
Carrington
Research Extension Center * North Dakota State University
P.O.
Box 531, Oakes, ND 58474-0531, Phone: (701) 742-2744, FAX: (701) 742-2700, E-mail: Kelly.c.Cooper@ndsu.edu
Oakes Irrigation
Research Site - Updates
Kelly
Cooper
The
Oakes Irrigation Research Site had a great year. Among the new projects and
developments is a new water supply
system. A
horizontal well was installed December 7, 2015. The horizontal well is a
relatively new way of extracting irrigation
quantities
of ground water in North Dakota. The well, as the name implies, runs
horizontally to the surface for several hundred
feet
buried some 20 feet deep by a modified trenching machine. The well pipe is
actually a poly sock wrapped plastic drain
tile 8
inches in diameter. Several of these wells have been installed in the Oakes
area during the last five years and most are
performing
adequately. Success is never a guarantee with any well, and horizontal wells
are no exception. Careful planning
is a must
and drilling test wells along the intended length of the well is a requirement.
At
the research site, we first looked up the logs of the test wells and existing
wells near our intended installation area
on the
North Dakota Water Commission website. These all looked positive, with sand or
gravel extending down to 30 feet below
the
surface. A requirement is to have no clay or silt layers between the
installation surface and the depth of the well. Most
commonly,
the top two feet of soil is excavated before installation which typically
removes finer material. Our next step
was
to pick a
location and dig test wells every 100 feet along the intended path. The test
wells are done by using high pressure
water
forced through a 1½ inch plastic pipe which is forced into the ground by hand.
The end of the pipe has a well screen
and a
special valve which allows water to exit out the end of the pipe, but closes
when suction is applied. The procedure also
shows how
fast the aquifer will “take” water, which is a good indicator of hydraulic
conductivity of the material and should
indicate
how fast water can come into the well. The new test wells revealed a layer of
silty clay four to six feet below the
ground
surface extending for a couple hundred feet along the intended path of the
well. Therefore, we decided to remove six
feet of
material. This not only removed the fine textured material so it would not get
mixed in next to the well pipe, but would
place the
pipe farther into the aquifer. The water table at the time of installation was
approximately 11 feet below ground level.
The trench
was six feet deep, 15 feet wide, and 800 feet long plus a ramp which allowed
the trencher to enter and exit.
Installation
started with the attachment of the standpipe to the trencher. The drain tile was
then threaded through the
trencher,
much like threading a sewing machine. The drain tile or well pipe was then
attached at the bottom of the stand pipe
at a 90
degree angle. With the standpipe loosely connected to the trencher, the
trencher digging chain is activated and the
trencher
digs its way into the ground as it is rotated into the vertical position. Once
vertical, the trenching machine begins to
move,
leaving the standpipe behind, stringing out the drain tile 20 feet below. The
entire process took nearly 3½ hours to install
the 800
feet of tile. After conferring with several interested parties, we decided to
tail up the end of the tile to ground surface
at the end
of the well to allow access. Garrison Diversion Conservancy District has been
cleaning its drain tiles on a regular
basis in
the Oakes test area, and this will allow them to clean this well, if needed.
Also, since this well is a relatively new
technology,
there may be utility in allowing access for various test equipment that could
be placed in the well to monitor
flow
rates, iron bacteria build up, or silt infiltration.
Shortly
after installation, the well was test pumped at 550 gallons per minute for 3½
hours. The draw down was 4½ feet
and
remained stable during the pumping period. We are working closely with the
North Dakota Water Commission to develop
a
monitoring plan that will hopefully help us understand how to best utilize
these types of wells in our area and elsewhere around
the
state. Many areas have adequate water,
but drilling and connecting multiple wells is prohibitively expensive or not
possible.
The
horizontal well system is another option to utilize water for beneficial purposes.
Starting point of the horizontal
well installation
Midpoint of the well installation and
completed well installation
Another
major improvement at the site was the installation of a new lateral irrigator.
The new system is equipped to apply
water with
a variable-rate control system. This simply means if we have a plot that does
not need water, for instance a dry edible
bean plot
that is mature, and is beside a potato plot that still needs water, the nozzles
will stop delivering water at the bean plot,
while
nozzles remain operating on the potato plot. It also can put ¾ inch of water on
one plot, and ½ inch on another. This system
will
improve our quality of research and allow different types of investigations on
water use. The new irrigation system will sustain
the basic
needs on the project and offer many new opportunities well into the future.
We
also acquired a new (used) Almaco plot combine which will serve us very nicely.
The used machine has been outfitted
with a
brand new automated weighing and grain moisture testing system to collect
sample data as we harvest the plots. The combine
has a corn
head and also a straight head that can be used for soybeans or small grain.
We
would like to thank the North Dakota Corn Council, North Dakota Soybean Council,
and the
North
Dakota State Water Commission for partial financial support of these
improvements.
Oakes Irrigation Research Site
Variety trials
Crop index Home page Report 2015